Electrical and Plumbing Systems in Container Houses
Quick answer

Specify voltage, frequency and plug type by destination at order stage; a container house cannot be converted cheaply on site. Electrical work should include a distribution board with RCD protection, labelled circuits, earthing and correctly sized cable for the load. Plumbing needs a supply point, pressure regulation, a hot water source, vented drainage with a fall of about 1-2 percent, and frost protection where the unit will be used in winter.

Services are where a well-built unit becomes an uncomfortable one. The failures are predictable: wrong voltage, undersized cable, no earth, drains that do not fall, and pipes that freeze in the first cold snap.

Electrical specification

ItemWhat to state
SupplyVoltage, frequency, single or three phase, total connected load
SocketsType and count per room
ProtectionMain breaker, RCD/GFCI, individual circuit breakers
LightingFixture type, colour temperature, switching layout
AC provisionUnit size, indoor position, drainage route, dedicated circuit
EarthingEarth bar, bonding of the steel frame, earth electrode at site

Standards by market

Europe and most of Asia use 230 V 50 Hz with IEC-based devices; the US uses 120/240 V 60 Hz with UL-listed devices; Australia uses 230/240 V 50 Hz with AS/NZS devices. The distribution board, sockets, and even the cable colour code differ. This is a factory decision, not a site one.

Plumbing layout

  • Wet core grouping: keep the shower, WC and basin on one wall so drainage runs are short and share a vent.
  • Supply: a single entry point with a stop valve and a pressure-reducing valve if the site main exceeds about 4 bar.
  • Hot water: electric storage or instantaneous; state the capacity and the circuit.
  • Drainage: 1-2 percent fall, traps at every fixture, vent pipe to atmosphere, and a clear route for the main outlet.
  • Frost protection: lagging, trace heating on exposed runs, or draining the system in unoccupied periods.

Commissioning checks

Insulation resistance and earth continuity on every circuit, RCD trip test, polarity check, water pressure test at 1.5 times working pressure, drain flow test with all fixtures running, and a hot water temperature check. Record the results; they belong in the handover file and are the first thing an inspector asks for.

What to send with the order

Country and voltage, plug type, total load and appliance list, water supply pressure, whether a tank is needed, and the winter minimum temperature. Five lines that prevent most commissioning problems.

Related: installation guide, fire rating, space capsule houses.

Need this priced for your project?

Send the unit type, quantity, destination port and any layout drawing. We reply with a specification-matched quotation and lead time, usually within one working day.

Request a quotation WhatsApp our team

Related: all container house products · custom container house · contact

Next step: get a real quotation

Tell us the destination port and the quantity, and we send a priced offer with drawings and a loading plan. Most enquiries are answered within one working day.

FAQ

Can a 220 V unit be used in the USA?
Not directly. Appliances, sockets and protection devices are built for 120/240 V 60 Hz, and UL listing is part of most inspections. Order the unit wired for the destination.
How is water supplied to a container house?
Usually from a site main via a pressure-reducing valve, or from a tank with a pump. Specify the connection point, pressure range and whether the tank is inside or outside the unit.
What fall is needed for drainage?
Typically 1-2 percent on horizontal runs, with vents at fixtures and a trap for each connection. Floors are built with a fall in wet areas; retrofitting a fall on site is not practical.